Project progress
Platform group · Q2 delivery board
58%
of all tasks done
7 projects · 356 tasks · 6 blocked · 1 overdue · 1 complete
Linwood Carter · due Mar 27 · 10 days late
Denise Runte DVM · due Apr 10 · 4 days left
Elizabeth Metz · due Apr 17 · 11 days left
Faith Harber · due Jun 30 · 85 days left
Brett Langosh · due May 8 · 32 days left
Hugo Emard · due May 15 · 39 days left
Bria Konopelski · due Apr 30 · 24 days left
done207 · 58%in progress39 · 11%blocked6 · 2%not started104 · 29%schedule line
Point at a project — or focus the rail and use ↑ and ↓ — to break its bar into counts and shares.
Each bar is one project's tasks, split into done, in progress, blocked and not started; bare track is work nobody has started. The four shares are whole per cents apportioned by largest remainder, so they add to exactly 100 and a segment holding real work never prints 0%. The tick is the schedule line — where a straight run from the start day to the due day says the project should be today. Health is derived from those numbers, never supplied: unscoped when no tasks are counted, complete when nothing is open, overdue past the due day, blocked while any task is blocked, at risk more than 10 points behind the schedule line, on track otherwise, and no schedule when the dates do not describe a window to draw a line in — the row says which date broke. Days are counted between calendar days, so nothing here moves with a time zone or a daylight-saving change. Rows run worst first: overdue, blocked, at risk, unscoped, no schedule, on track, complete.
Project progress: Platform group · Q2 delivery board. 7 projects, 356 tasks in scope. 58% of all the work is done. Across the whole board that is 58% done, 11% in progress, 2% blocked, 29% not started — whole per cents apportioned by largest remainder, so the four add to exactly 100. Read on Apr 6, 2026. 1 overdue, 2 holding blocked work, 2 at risk, 1 complete. Next date on the board: Design system v2 on Mar 27, 2026, 10 days late. Rows run worst first: overdue, blocked, at risk, unscoped, no schedule, on track, complete. Every project is listed in the table below.
Every project on the board with its owner, its dates, the four counts and their shares, the completion figure, where the schedule line stands today, and the health worked out from them.| Project | Owner | Started | Due | Days left | Done | In progress | Blocked | Not started | Total | Complete | Schedule line | Health | Why |
|---|
| Design system v2 | Linwood Carter | Jan 5, 2026 | Mar 27, 2026 | 10 days late | 54 (83%) | 3 (5%) | 2 (3%) | 6 (9%) | 65 | 83% | 100% | Overdue | 10 days past Mar 27, 11 tasks still open, 2 blocked |
|---|
| Billing rewrite | Denise Runte DVM | Feb 2, 2026 | Apr 10, 2026 | 4 days left | 31 (67%) | 6 (13%) | 4 (9%) | 5 (11%) | 46 | 67% | 94% | Blocked | 4 tasks blocked and not moving · 4 days left |
|---|
| Atlas data migration | Elizabeth Metz | Jan 12, 2026 | Apr 17, 2026 | 11 days left | 48 (62%) | 12 (15%) | 0 (0%) | 18 (23%) | 78 | 62% | 88% | At risk | 26 points behind the schedule line · 11 days left |
|---|
| Search relevance | Faith Harber | Mar 16, 2026 | Jun 30, 2026 | 85 days left | 0 (0%) | 4 (10%) | 0 (0%) | 36 (90%) | 40 | 0% | 20% | At risk | 20 points behind the schedule line · 85 days left |
|---|
| Partner API sandbox | Brett Langosh | not recorded | May 8, 2026 | 32 days left | 9 (35%) | 5 (19%) | 0 (0%) | 12 (46%) | 26 | 35% | no schedule line | No schedule | no start date, so there is no schedule line to judge it against · 32 days left |
|---|
| Mobile onboarding | Hugo Emard | Mar 2, 2026 | May 15, 2026 | 39 days left | 24 (40%) | 9 (15%) | 0 (0%) | 27 (45%) | 60 | 40% | 47% | On track | 7 points behind, inside the 10-point band · 39 days left |
|---|
| SOC 2 evidence | Bria Konopelski | Feb 16, 2026 | Apr 30, 2026 | 24 days left | 41 (100%) | 0 (0%) | 0 (0%) | 0 (0%) | 41 | 100% | 67% | Complete | nothing left open, 24 days before the date |
|---|